* On 2013-12-19 at 16:13 GMT, Izumi Tsutsui wrote:

> jperkin@ wrote:
> 
> > 2-3 days is nowhere near long enough to perform even an update bulk
> > build on a slow to medium platform, get the results and be able to act
> > upon them before the freeze.
> 
> I'm asking about update of leaf packages.
> Is it so serious on bulk build?

While it is clearly less of an issue to update leaf packages, the main
point still stands.  2 days is not long enough for a bulk build to run
and for you to act on any fallout you may have caused by updating the
package.

-- 